Harald, SA., has done a cost analysis for its production of bumper stickers. The following activities and cost drivers have been developed:  Activity  Cost Formula  Maintenance £11,000+£0.11 per machine hour  Machining £25,000+£0.50 per machine hour  Setups £50 per batch  Purchasing £200+£45 per purchase order \begin{array}{ll}\text { Activity } & \text { Cost Formula } \\\text { Maintenance } & £ 11,000+£ 0.11 \text { per machine hour } \\\text { Machining } & £ 25,000+£ 0.50 \text { per machine hour } \\\text { Setups } & £ 50 \text { per batch } \\\text { Purchasing } & £ 200+£ 45 \text { per purchase order }\end{array} Following are the actual costs of producing 85,000 stickers: 5,000 machine hours; 10 batches; 20 purchase orders  Maintenance £11,500 Machining 28,300 Setups 550 Purchasing 1,000\begin{array}{lr}\text { Maintenance } & £ 11,500 \\\text { Machining } & 28,300 \\\text { Setups } & 550 \\\text { Purchasing } & 1,000\end{array}
-Refer to Figure 16-3. What is the budget variance for machining in an activity-based performance report?


A) £50 F
B) £50 U
C) £800 U
D) none of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents