Figure 11-2
Owens Ltd. produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications) . Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers: Activity drivers for each activity have been identified and their practical capacities listed: The costs of facility-level activities are assigned using machine hours.
-Refer to Figure 11-2. What is the cost pool overhead rate for the unit-level activities?
A) £80.00 per machine hour
B) £13,500.00 per setup
C) £17.20 per machine hour
D) £97.20 per machine hour
Correct Answer:
Verified
Q6: Riley, SA., has identified the following
Q7: All of the following are unit-based activity
Q8: Figure 11-2
Owens Ltd. produces specially machined
Q9: If activity-based costing is used, insurance on
Q10: Maintenance of the production equipment would be
Q12: If activity-based costing is used, electricity usage
Q13: Figure 11-2
Owens Ltd. produces specially machined
Q14: Which of the following quantities is an
Q15: If activity-based costing is used, product inspections
Q16: Figure 11-1
Ubben Manufacturing uses an activity-based
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents