The post-audit is used to
A) Improve cash flow forecasts.
B) Stimulate management to improve operations and bring results into line with forecasts.
C) Eliminate potentially profitable but risky projects.
D) All of the answers above are correct.
E) Answers a and b are correct.
Correct Answer:
Verified