A company just paid $10 million for a feasibility study. If the company goes ahead with the project, it must immediately spend another $100 million now, and then spend $20 million in one year. In two years it will receive $80 million, and in three years it will receive $90 million. If the cost of capital for the project is 11 percent, what are the project's NPV and IRR?


A) NPV = $2.72 million; IRR = Two positive IRRs.
B) NPV = $2.72 million; IRR = 16%.
C) NPV = $12.72 million; IRR = Two positive IRRs.
D) NPV = $12.72 million; IRR = 16%.
E) None of the above.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents