In selecting an accounting method for a newly contracted long-term construction project, the principal factor to be considered should be
A) the terms of payment in the contract.
B) the degree to which a reliable estimate of the costs to complete and extent of progress toward completion is practicable.
C) the method commonly used by the contractor to account for other long-term construction contracts.
D) the inherent nature of the contractor's technical facilities used in construction.
Correct Answer:
Verified
Q28: Under the completed-contract method
A) revenue, cost, and
Q29: Dot Point, Inc. is a retailer of
Q30: The process of formally recording or incorporating
Q31: When goods or services are exchanged for
Q32: In accounting for a long-term construction-type contract
Q34: The principal advantage of the completed-contract method
Q35: All units in a multiple-deliverable arrangement are
Q36: The revenue recognition principle provides that revenue
Q37: A sale should not be recognized as
Q38: An alternative available when the seller is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents