Use the following information for questions 83 and 84.
Eilert Construction Company had a contract starting April 2015, to construct a $21,000,000 building that is expected to be completed in September 2016, at an estimated cost of $19,250,000. At the end of 2015, the costs to date were $8,855,000 and the estimated total costs to complete had not changed. The progress billings during 2015 were $4,200,000 and the cash collected during 2015 was $2,800,000. Eilert uses the percentage-of-completion method.
-At December 31, 2015, Eilert would report Construction in Process in the amount of
A) $9,660,000.
B) $8,855,000.
C) $8,260,000.
D) $805,000.
Correct Answer:
Verified
Q80: Use the following information for questions 65-68:
Seasons
Q81: Sutton Company sells plasma-screen televisions on an
Q82: Daily, Inc. appropriately used the installment method
Q83: Hiser Builders, Inc. is using the
Q84: Use the following information for questions 99
Q86: Use the following information for questions 86
Q87: Use the following information for questions 96-98.
During
Q88: Use the following information for questions 96-98.
During
Q89: Use the following information for questions 86
Q90: Use the following information for questions 96-98.
During
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents