During 2012, Crema Manufacturing expected Job 59 to cost $300,000 of overhead, $500,000 of material, and $200,000 in labour.Crema applied overhead based on direct labour cost.Actual production required an overhead cost of $280,000, $550,000 in materials used; and $220,000 in labour.All of the goods were completed.How much is the amount of over/under applied overhead?
A) $50,000 under-applied
B) $50,000 over-applied
C) $20,000 under-applied
D) $20,000 over-applied
Correct Answer:
Verified
Q156: A company assigned overhead to work in
Q157: Cal, Inc.showed the following amounts in its
Q158: Crowl, Inc.determined that $200,000 of manufacturing overhead
Q159: In applying costs using a pre-determined overhead
Q160: When monthly financial statements are prepared, where
Q162: Which one of the following is true
Q162: What is the rationale behind applying overhead
Q163: Tra Corporation is analyzing its account balances
Q165: When overhead is under-applied at the end
Q166: If the financial statements of Sushi Show,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents