Concrete Was Ordered for a Sidewalk Which Measures 200' Long

Question 54

Short Answer

Concrete was ordered for a sidewalk which measures 200' long by 3' wide and poured to a depth of 4". How many cubic yards of concrete are required for the walk? (Round to next higher cubic yard.)
V = Length × Width × Depth

Correct Answer:

verifed

Verified