Puckett Inc.risk-adjusts its WACC to account for project risk.It uses a risk-adjusted project cost of capital of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects.Which of the following independent projects should Puckett accept, assuming that the company uses the NPV method when choosing projects?
A) Project B, which has below-average risk and an IRR = 8.5%.
B) Project C, which has above-average risk and an IRR = 11%.
C) Without information about the projects' NPVs we cannot determine which project(s) should be accepted.
D) All of these projects should be accepted.
E) Project A, which has average risk and an IRR = 9%.
Correct Answer:
Verified
Q64: Spot-Free Car Wash is considering a
Q65: Which of the following procedures best accounts
Q66: The standard deviation is a better measure
Q67: Erickson Inc.is considering a capital budgeting project
Q68: If a firm's projects differ in risk,
Q70: Tallant Technologies is considering two potential
Q71: Because of differences in the expected returns
Q72: Sensitivity analysis measures a project's stand-alone risk
Q73: Laramie Labs uses a risk-adjustment when
Q74: McLeod Inc.is considering an investment that has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents