Activities following a node
A) can begin as soon as any activity preceding the node has been completed.
B) have an earliest start time equal to the largest of the earliest finish times for all activities entering the node.
C) have a latest start time equal to the largest of the earliest finish times for all activities entering the node.
D) None of the alternatives is correct.
Correct Answer:
Verified
Q17: The latest finish time for an activity
Q18: Precedence relationships among activities is critical in
Q19: Activities require time to complete while events
Q26: A critical activity is
A)an activity that consumes
Q26: Which is not a significant challenge of
Q27: Activities K,M,and S immediately follow activity H,and
Q31: For an activity with more than one
Q32: Activities G,P,and R are the immediate predecessors
Q33: The earliest start time rule
A)compares the starting
Q34: Which of the following is a general
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents