The length of time an activity can be delayed without affecting the project completion time is the slack.
Correct Answer:
Verified
Q15: It is possible to have more than
Q16: It is normal for activities on the
Q17: The latest finish time for an activity
Q18: A path through a project network must
Q19: A critical activity can be part of
Q21: Arcs in a project network indicate
A)completion times.
B)precedence
Q22: The main difference between CPM and PERT
Q23: PERT and CPM
A)are most valuable when a
Q24: When activity times are uncertain,
A)we assume they
Q25: Activities following a node
A)can begin as soon
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents