Use the Following Information for Questions

Question 50

Short Answer

Use the following information for questions.The contract calls for progress billings and payments of $620,000 each quarter.The total contract price is $7,440,000 and Seasons estimates total costs of $7,100,000.Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2010.
-Seasons Construction completes the remaining 25% of the building construction on December 31, 2012, as scheduled.At that time the total costs of construction are $7,500,000.What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Seasons will recognize for the year ended December 31, 2012?
Use the following information for questions.The contract calls for progress billings and payments of $620,000 each quarter.The total contract price is $7,440,000 and Seasons estimates total costs of $7,100,000.Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2010. -Seasons Construction completes the remaining 25% of the building construction on December 31, 2012, as scheduled.At that time the total costs of construction are $7,500,000.What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Seasons will recognize for the year ended December 31, 2012?

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents