Use the following information for questions.The contract calls for progress billings and payments of $620,000 each quarter.The total contract price is $7,440,000 and Seasons estimates total costs of $7,100,000.Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2010.
-Seasons Construction completes the remaining 25% of the building construction on December 31, 2012, as scheduled.At that time the total costs of construction are $7,500,000.What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Seasons will recognize for the year ended December 31, 2012?
Correct Answer:
Verified
Q46: The following information relates to questions
Cooper
Q48: Adler Construction Co.uses the percentage-of-completion method.In 2010,
Q49: On July 1, 2011, Panther, Inc.sold goods
Q51: On January 1, 2012, Hood Company sold
Q53: Hayes Construction Corporation contracted to construct a
Q55: Types of franchising arrangements include all of
Q55: Some of the initial franchise fee may
Q64: Continuing franchise fees should be recorded by
Q66: Occasionally a franchise agreement grants the franchisee
Q73: A franchise agreement grants the franchisor an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents