Use the following information for questions.
Eilert Construction Company had a contract starting April 2011, to construct a $15,000,000 building that is expected to be completed in September 2012, at an estimated cost of $13,750,000.At the end of 2011, the costs to date were $6,325,000 and the estimated total costs to complete had not changed.The progress billings during 2011 were $3,000,000 and the cash collected during 2011 was $2,000,000.Eilert uses the percentage-of-completion method.
-For the year ended December 31, 2011, Eilert would recognize gross profit on the building of
A) $0.
B) $527,083.
C) $575,000.
D) $675,000.
Correct Answer:
Verified
Q71: Use the following information for questions.
Gorman Construction
Q72: Hiser Builders, Inc.is using the cost-recovery method
Q73: Use the following information for questions.
Gorman Construction
Q74: Use the following information for questions.
Gomez, Inc.began
Q75: Spenders Company is an experienced home appliance
Q77: Spenders Company is an experienced home appliance
Q78: Use the following information for questions.
Kiner, Inc.began
Q79: Lark Corp.has a contract to construct a
Q80: Wynn, Inc.has a contract to construct a
Q81: On January 1, 2012 Dairy Treats, Inc.entered
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents