Ritz Company expects to sell 24,000 units of finished goods over the next 6-month period. The company has 10,000 units on hand and its managers want to have 14,000 units on hand at the end of the period. To produce one unit of finished product, two units of direct materials are needed. Ritz has 100,000 units of direct material on hand and has budgeted for an ending inventory of 110,000 units.
What is the amount of direct material to be purchased (in units) ?
A) 38,000
B) 46,000
C) 66,000
D) 18,000
Correct Answer:
Verified
Q25: (Appendix 10A) Conner Company is a
Q26: In zero-based budgeting, managers justify budget amounts
Q27: One disadvantage of participative budgeting is employees'
Q28: Participative budgeting involves customers and managers at
Q29: When managers intentionally set budgeted costs too
Q31: The principles of activity-based costing can be
Q32: (Appendix 10A) Conner Company is a
Q33: Horton Company produces and sells two products:
Q34: (Appendix 10A) Conner Company is a
Q35: Kaizen budgeting is designed to improve quality
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents