Multiple Choice
Sparkle Company uses job costing and applies overhead using an actual costing system using direct labour hours as the allocation base. This period's estimated overhead cost is $400,000, estimated direct labour cost is $500,000 and estimated direct labour hours are 25,000. This period's actual overhead cost was $420,000, actual direct labour cost was $390,000, and actual direct labour hours were 20,000.
What is the overhead allocation rate?
A) $21/hour
B) $10/hour
C) $16/hour
D) $18/hour
Correct Answer:
Verified