• The overhead is allocated to jobs using an estimated rate applied to direct labour hours. The budget for the year called for $180,000 of overhead cost and 60,000 direct labour hours.
• Accounts payable is used for materials only. The balance on 9/1 was $6,000. September's payments were $40,000.
• September 1 finished goods inventory was $11,000.
• Cost of jobs completed in September was $89,000.
• On September 30 there was a single job unfinished, consisting of $1,800 (300 hours) of direct labour and $2,600 of direct material.
• 5,200 direct hours were worked during September. All workers earn the same rate of pay.
• All actual overhead costs incurred have been recorded.
Over- or underapplied overhead for September was:
A) $800 underapplied
B) 800 overapplied
C) $1,600 underapplied
D) $1,600 overapplied