Opportunity costs are:
A) Benefits foregone from one project because another project is chosen
B) Irrelevant
C) The same as sunk costs
D) Easy to value
Correct Answer:
Verified
Q118: Marginal cost is:
A) The average cost per
Q119: If firm A has a learning curve
Q120: If we want to estimate the cost
Q121: All of the following are assumptions for
Q122: All of the following are true about
Q124: Cost drivers are:
A) Activities that cause costs
Q125: All of the following are examples of
Q126: Direct costs are:
A) Costs that need to
Q127: Sunk costs are:
A) The same as opportunity
Q128: Indirect costs are:
A) Costs that need to