Fredrika has been asked to develop a Pareto Priority Index for a process improvement project. She and her team have researched the situation and developed the following parameters:
Estimated lifetime cost savings: $200,000
Total estimated cost: $50,000
Forecasted project success probability: 70%
Estimated project duration: 2 years
Given this information, what is the Pareto Priority Index?
A) 1.4
B) 11.43
C) .25
D) 2.8
E) 4.0
Correct Answer:
Verified
Q4: An advantage of factor rating for project
Q5: Which of the following problem statements includes
Q6: Project Thunderbolt will incur $30,000 in cost
Q7: If a team wishes to use brainstorming
Q8: Which of these is a potential disadvantage
Q9: Each of the following is an example
Q10: Company B is considering implementing a new
Q11: Which of the following tools for causal
Q13: A planning committee is attempting to decide
Q14: NPV is a measure of:
A) The
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents