A national circus organization performs in outdoor locations in approximately 35 cities each year. The same technical crew is used to set up and take down rides for all locations. Given that the set up for the rides is exactly the same at each location, and set up at the first location for a particular ride takes 85 minutes, how long would the set up for the same ride take at the 8th location? Assume a 75 percent learning rate and round to two places to the right of the decimal.
A) 11.35 minutes
B) 35.860 minutes
C) 47.81 minutes
D) 26.90 minutes
E) 63.75 minutes
F) None of the above
Correct Answer:
Verified
Q3: Which of the following is a reasonable
Q4: All of the following are advantages to
Q5: Which of the following depends) on the
Q6: Which of the following WBS formats is
Q7: A consumer electronics company is planning a
Q8: Which of the following is not a
Q9: A new project manager is taking over
Q10: Which of these is the best guideline
Q12: Which WBS approach is most likely to
Q13: Your school's recruiting staff is planning
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents