Solved

The Table Below Shows PERT Estimates Te) for Activities a Through

Question 20

Multiple Choice

The table below shows PERT estimates te) for activities A through E.
 Time estimates (days)  \text { Time estimates (days) }
 Activity t(o) t(m) t(p) t(e) A459?B137?C3610?D2812?E146?\begin{array}{|c|c|c|c|c|}\hline \text { Activity }&t(o) &t(m) &t(p) &t(e) \\\hline \mathrm{A} & 4 & 5 & 9 & ? \\\hline \mathrm{B} & 1 & 3 & 7 & ? \\\hline \mathrm{C} & 3 & 6 & 10 & ? \\\hline \mathrm{D} & 2 & 8 & 12 & ? \\\hline \mathrm{E} & 1 & 4 & 6 & ? \\\hline\end{array}
Based on the table above, the te) for activities A, B and C are: .


A) 5 days, 3 days, 6 days
B) 5.500 days, 3.333 days, 6.167 days
C) 6 days, 3.667 days, 6.333 days
D) 3.167 days, 5.333 days, 1.833 days
E) 3 days, 1.667 days, 1.833 days
F) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents