Brothers Construction Uses a Predetermined Overhead Rate of $6

Question 103

Multiple Choice

Brothers Construction uses a predetermined overhead rate of $6.00 per direct labor hour.Budgeted overhead was $720,000 and actual overhead incurred was $700,000.Actual direct labor hours worked were 125,000 hours.How many labor hours did Brothers plan to work during the year?


A) 120,000 hours
B) 116,667 hours
C) 20,833 hours
D) Cannot be determined from the information given