Keller Company has a materials price standard of $2.00 per pound. Five thousand pounds of materials were purchased at $2.20 a pound. The actual quantity of materials used was 5,000 pounds, although the standard quantity allowed for the output was 4,500 pounds.
Keller Company's materials price variance is
A) $100 U.
B) $1,000 U.
C) $900 U.
D) $1,000 F.
Correct Answer:
Verified
Q82: The formula for the materials quantity variance
Q88: The formula for the materials price variance
Q90: Keller Company has a materials price standard
Q96: The total variance is $25,000. The total
Q97: A company uses 8,400 pounds of materials
Q98: Keller Company has a materials price standard
Q107: The investigation of materials price variance usually
Q109: Labor efficiency is measured by the
A) materials
Q112: The investigation of a materials quantity variance
Q114: An unfavorable labor quantity variance may be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents