Humphreys, Inc. uses standard costing for its one product, baseball bats. The standards call for 3 board-feet of wood at $1.40 per board-foot, and 45 minutes of work at $12 per hour per bat. Total manufacturing overhead costs were estimated at $5,250, of which the variable portion was $0.50 per bat and the fixed portion was $0.75 per bat with an estimate of 4,200 bats to be produced. Humphreys identifies price variances at the earliest possible point in time.
During March, the company had the following results:
Direct labor used = 3,200 hours at a cost of $37,760
Actual manufacturing overhead fixed costs = $3,000
Actual manufacturing overhead variable costs = $2,050
Bats produced = 4,000
Instructions
Compute the following variances for March.
1. Labor quantity variance
2. Total labor variance
3. Overhead controllable variance
4. Overhead volume variance
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q191: George Company has a standard costing system.
Q192: Hurley, Inc. manufactures widgets for distribution. The
Q193: National Sporting Goods Company manufactures aluminum baseball
Q194: Jamison Industries provided the following information about
Q197: The following direct labor data pertain to
Q198: Wagner Company developed the following standard
Q199: The standard cost of Product 245 manufactured
Q201: Match the items in the two columns
Q236: In developing a standard cost for direct
Q240: A _ is expressed as a unit
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents