Solved

The Following Two Questions Use the Information in This MRP

Question 28

Multiple Choice

The following two questions use the information in this MRP record. The lead time is 3 weeks.
 Week 12345 Gross requirements 6050607020 Scheduled receipts 100 Projected available 40903040 Net requirements Planned  order receipt Planned  order release 100\begin{array}{llllll}\text { Week } & 1 & 2 & 3 & 4 & 5 \\\text { Gross requirements } & 60 & 50 & 60 & 70 & 20 \\\text { Scheduled receipts } & & 100 & & &\\\text { Projected available }&40&90&30&&40\\\text { Net requirements Planned }\\\text { order receipt Planned }\\\text { order release } \quad100\end{array}
-The projected available to be shown in week four is:


A) 0
B) 60
C) 70
D) 80
E) none of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents