In the short run, capacity can be altered by any of the following EXCEPT:
A) scheduling overtime
B) selecting alternate routings
C) reallocating the work force
D) purchasing new equipment
E) subcontracting out
Correct Answer:
Verified
Q13: Information on the standard times for an
Q14: Rated capacity is calculated taking into account
Q15: Which of the following is NOT an
Q16: (Available time) × (utilization) × (efficiency) is
Q17: The ratio of standard hours of work
Q18: Which of the following is the best
Q19: A work center consists of 2 machines
Q21: The difference between backward scheduling and forward
Q22: Available capacity planned to exceed capacity required
Q23: In one week a work center produces