Sully Company uses 3,000 yards of canvas each day to make tents. It usually takes ten days from the time Sully orders the material to when it is received. If Sully's desired safety stock is 12,000 yards, what is Sully's order point?
A) 12,000 yards
B) 21,000 yards
C) 30,000 yards
D) 42,000 yards
Correct Answer:
Verified
Q4: What is the objective of the economic
Q6: The data used to calculate the order
Q7: The following data pertains to Western Company's
Q10: Janet is the purchasing agent at Frameco
Q10: Expected annual usage of a particular raw
Q11: To effectively control materials,a business must maintain:
A)Limited
Q14: The following data refer to various annual
Q15: Marley Company hired a consultant to help
Q16: The employee who is responsible for preparing
Q17: Expected annual usage of a particular raw
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents