Which of the following is not a direct acquisition cost of an IT initiative?
A) Cost of hardware
B) Cost of business disruption
C) Cost of project management
D) Cost of software development
Correct Answer:
Verified
Q14: The benefits of an IT project are
Q15: Net present value techniques compute the unique
Q16: Benefits are often estimated without complete information.
Q17: Which of the following is an example
Q18: Which of the following is not a
Q20: In making the business case for an
Q21: Benefits of IT initiatives should be measured
Q22: If the implementation costs greatly exceed the
Q23: Which of the following would not help
Q24: Acquisition costs for an IT initiative include