Dart Company developed the following standard costs for its product for 2016:
The company expected to work at the 120,000 direct labor hours level of activity and produce 60,000 units of product.
Actual results for 2016 were as follows:
56,800 units of product were actually produced.
Direct labor costs were $1,092,000 for 112,000 direct labor hours actually worked.
Actual direct materials purchased and used during the year cost $1,108,800 for 231,000 pounds.
Total actual manufacturing overhead costs were $680,000.
Instructions
Compute the following variances for Dart Company for 2016 and indicate whether the variance is favorable or unfavorable.
1. Direct materials price variance.
2. Direct materials quantity variance.
3. Direct labor price variance.
4. Direct labor quantity variance.
5. Overhead controllable variance.
6. Overhead volume variance.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q143: The perspectives included in the balanced scorecard
Q162: Riggins, Inc. manufactures one product called tybos.
Q163: Seacoast Company provided the following information about
Q167: Engines Done Right Co. is trying to
Q168: Hector Company has developed the following
Q169: Lumberman Manufacturing provided the following information about
Q181: During March Patt Inc. purchases and uses
Q189: Labor data for making one pound of
Q191: Standards based on the optimum level of
Q212: Prescott Manufacturing manufactures widgets for distribution. The
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents