Forrest Painting Service has budgeted the following time and material for 2016:
Forrest budgets 4,000 hours of paint time in 2016 and will charge a profit of $12 per hour, in addition to a 25% markup on the cost of paint.
On February 15, 2016, Forrest is asked to prepare a price estimate to paint a building. Forrest estimates that this job will take 12 labor hours and $500 in paint.
Instructions
1. Compute the labor rate for 2016.
2. Compute the material loading charge rate for 2016.
3. Prepare a time-and-material price estimate for painting the building.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q105: Variable costs of units sold internally will
Q108: The maximum transfer price from the buying
Q118: Rita Corporation produces commercial fertilizer spreaders. The
Q121: Chuck's Classic Cars restores classic automobiles to
Q122: Spirit Manufacturing is a division of Birch
Q124: Green Yard Company, a division of Lawn
Q125: In the cost-plus pricing formula, the target
Q126: The three approaches for determining a transfer
Q127: The Pacific Company is a multidivisional company.
Q128: The formula for the minimum transfer price
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents