For an activity with more than one immediate successor activity,its latest finish time is equal to the
A) largest latest finish time among its immediate successors.
B) smallest latest finish time among its immediate successors.
C) largest latest start time among its immediate successors.
D) smallest latest start time among its immediate successors.
Correct Answer:
Verified
Q26: A critical activity is
A)an activity that consumes
Q27: Activities K,M,and S immediately follow activity H,and
Q28: Activities with zero slack
A)can be delayed.
B)must be
Q29: In deciding which activities to crash,one must
Q30: Slack equals
A)LF - EF.
B)EF - LF.
C)EF -
Q32: Activities G,P,and R are the immediate predecessors
Q33: The earliest start time rule
A)compares the starting
Q34: Which of the following is a general
Q35: Which of the following is NOT a
Q36: To calculate an activity's latest finish time,you
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents