A manufacturer makes two products,doors and windows.Each must be processed through two work areas.Work area #1 has 60 hours of available production time per week.Work area #2 has 48 hours of available production time per week.Manufacturing of a door requires 4 hours in work area #1 and 2 hours in work area #2.Manufacturing of a window requires 2 hours in work area #1 and 4 hours in work area #2.Profit is $8 per door and $6 per window.
a.
Define decision variables that will tell how many units to build (doors and windows)per week.
b.Develop an objective function that will maximize total profit per week.
c.Develop production constraints for work area #1 and #2.
Correct Answer:
Verified
Q43: A computer rework center has the capacity
Q44: Consider a department store that must make
Q45: To establish a driver education school,organizers must
Q46: In this portion of an Excel spreadsheet,the
Q47: An author has received an advance against
Q48: Jane Persico,facility engineer at the El Paso
Q50: A university schedules summer school courses based
Q51: As part of their application for a
Q52: Zipco Printing operates a shop that has
Q53: There is a fixed cost of $50,000
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents