A Chemical Company Is Trying to Decide Whether to Build

Question 90

Essay

A chemical company is trying to decide whether to build a pilot plant now for a new chemical process or to build the full plant now. If they build a pilot plant now, they could expand it later to a full plant or license the plant to another company. It would cost them $2 million to build the pilot plant and another $2 million later to expand it. If they build the full plant now it would cost $3.5 million to construct.

The returns they expect to get from the full production plant depend upon the market. They estimate there is a 60% chance the market will be robust, a 30% chance it will remain stable, and a 10% chance it will become stagnate. The returns are estimated to be $5 million if it is robust, $3 million if it is stable, and $1 million if it is stagnate.

Before they expand the pilot plant, they plan to conduct a comprehensive study. Based on past experience, they expect the study to report a 60% chance of favorable outcome for expansion and a 40% unfavorable chance. In either case they will have to decide whether to expand to a full plant or license the pilot plant. If the report is favorable and they license it, they expect to get $3 million. However, if the report is unfavorable and they license it, they will only get $1 million.

Develop a decision tree for this problem and determine the optimal decision strategy.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents