Solved

Altona City Opened a Landfill That It Elects to Account

Question 68

Essay

Altona City opened a landfill that it elects to account for in an enterprise fund.
-At the time the landfill was opened the government estimated total capacity of the landfill to be 5 million cubic feet, useful life to be 20 years, and total closure and postclosure costs to be $18 million.
-At the end of Year 1, the government reestimated total closure costs to be $18.3 million and estimated capacity to be same as the original estimate.
-At the end of Year 2, the government reestimated total capacity to be 4.8 million cubic feet and total closure costs to be $18.5 million.
-At the end of Year 3, the government reestimated useful life to be 17 years but capacity remained unchanged from the preceding year and closure and postclosure costs were estimated to be $18.4 million.
REQUIRED:
Prepare journal entries in the enterprise fund to record the following events.
b) During Year 1, the city estimates that 300,000 cubic feet of capacity were used. Record the landfill expense.
c) During Year 2, the city estimates that 650,000 cubic feet of capacity were used. Record the landfill expense.
d) During Year 3 the city installed equipment at a cost of $130,000. The equipment will be used in monitoring the landfill when it is closed.
e) During Year 3 the city estimates that 1,050,000 cubic feet of capacity were used. Record the landfill expense.

Correct Answer:

verifed

Verified

blured image (1,050,000/4,800,000) x $18....

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents