Jane Browning Purchased a Tract of Land and Contracted with a Builder

Question 49

Short Answer

Jane Browning purchased a tract of land and contracted with a builder to build an office building on the property. She also engaged other contractors for lighting, fencing, paving, etc.
Based on the following transactions, determine the total costs allocated to the land, building, and land improvements accounts.
a)Purchased land for $125,000.
b)Paid a contractor $150,000 to design and build the office building.
c)Paid a demolition company $20,000 to remove an old structure on the property.
d)Paid $15,000 in delinquent taxes on the property.
e)Paid $20,000 for fencing.
f)Paid $10,000 for paving.
g)Paid an electrical contractor $15,000 for outdoor lighting.
Cost of land \quad\quad\quad\quad\quad\quad ------
Cost of building \quad\quad\quad\quad\quad ------
Cost of land improvements \quad ------

Correct Answer:

verifed

Verified

Land = $125,000 + $20,000 + $1...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents