In the Context of Sequencing, the Earliest Due Date (EDD)

Question 11

Multiple Choice

In the context of sequencing, the earliest due date (EDD) rule:


A) minimizes the maximum number of jobs past due.
B) maximizes average flow time of jobs past due.
C) maximizes resource utilization of jobs past due.
D) minimizes the average processing time of jobs past due.

Correct Answer:

verifed

Verified