Solved

Tantramar Construction Has an October 31 Year End

Question 80

Multiple Choice

Tantramar Construction has an October 31 year end. On October 20 Tantramar received a payment from Cantech Industries in the amount of $25,000 as an advance on the construction for the new head office of Cantech. Construction was to have started October 25 but due to an early snowfall, construction did not start until November 7. Construction is scheduled to be completed December 31. Following the revenue recognition criteria, the revenue which Tantramar should record in its October 31 Financial Statements is


A) $10,000.
B) $5,000.
C) 0.
D) none of the above.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents