Short Answer
Tahiti Manufacturing recently purchased a new machine. The maintenance contractor recommended that this model should receive maintenance every 3,000- 6,000 hours of operation. If each maintenance check costs $220 and the machine is expected to provide 30,000 hours of service, what is the total savings of scheduling maintenance every 6,000 hours over 3,000 hours?