Extreme Wreaths, Inc., makes wreaths in batch sizes of 15 at a time. The cutting and assembly process takes 10 minutes per wreath, and the decorating process time is 7 minutes per wreath. It takes 5 minutes to move the wreaths from the cutting and assembly process to the decorating process.
In an effort to improve the lead time, the company has tried reducing the batch size to 10 units. The new process is as follows: cutting and assembly process-8 minutes. The decorating process is still 7 minutes per wreath. It takes 5 minutes to move the wreaths from the cutting and assembly process to the decorating process.
a. Compute the value-added, non-value-added, and the total lead times of the wreath process for both the old and new manufacturing processes.
b. Compute the value-added ratio for both the old and new processes. Round to one decimal place.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q124: Axelgold Company produces parts for the auto
Q125: A quality control activity analysis indicated the
Q126: Kwanika Co. operates in a lean manufacturing
Q127: Which of the following are features of
Q128: From the provided schedule of activity costs,
Q130: From the provided schedule of activity costs,
Q131: From the provided schedule of activity costs,
Q132: Peters Manufacturing Co. operates in a lean
Q133: Connally Company's Payroll Department required that every
Q134: Bright Lamp Company has budgeted its conversion
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents