Selected accounts with amounts omitted are as follows:
If the balance of Work in Process on August 31 is $220,000, what was the amount debited to Work in Process for direct materials in August?
A) $390,000
B) $170,000
C) $525,000
D) $580,000
Correct Answer:
Verified