Essay
A newly constructed water-treatment facility cost $2 million. It is estimated that the facility will need
revamping to maintain the original design specification every 30 years at a cost of $1 million. Annual repairs
and maintenance costs are estimated to be $100,000. At an interest rate of 6%, determine the capitalized cost of
the facility.