In a project, which of the following relations is true?
A) The Optimal Time is always greater than the Minimal Time.
B) The Optimal Time is always less than the Minimal Time.
C) The Optimal Time is always equal to the Minimal Time.
D) The Optimal Time is always greater than or equal to the Minimal Time.
E) The Optimal Time is always less than or equal to the Minimal Time.
Correct Answer:
Verified