After initial control chart construction, the second step to continue statistical monitoring of a process is?
A) Collect samples of size four or five periodically
B) Plot sample means and ranges on the control charts
C) If the process trends out of control, investigate the causes and eliminate assignable variations
D) Ensuring that the process is in control before beginning statistical monitoring
Correct Answer:
Verified
Q27: Producer's risk can result in what type
Q28: After initial control chart construction, the first
Q29: The A2 value for a sample size
Q30: A process with a mean output of
Q31: A process in which process variation fits
Q33: When a shipment is received from suppliers
Q34: A process with a mean output of
Q35: A process with a mean output of
Q36: A process in which process variation does
Q37: A process with a mean output of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents