Critical activities primarily govern what aspect of a project?
A) Project start time
B) Project completion time
C) Project budget
D) Project resource availability
Correct Answer:
Verified
Q20: The fourth step in both the CPM
Q21: If an activity has a late start
Q22: PERT relies on all of the following
Q23: The first step to crash a project
Q24: Activities on the critical path are referred
Q26: The time estimate that represents the time
Q27: The time estimate that represents the time
Q28: Activities on the critical path have slack
Q29: A project has four activities. Activity A
Q30: The time estimate that represents the best