The optimistic, most likely, and pessimistic completion times are used to determine the?
A) Least likely completion time
B) Maximum completion time
C) Minimum completion time
D) Expected completion time
Correct Answer:
Verified
Q28: Activities on the critical path have slack
Q29: A project has four activities. Activity A
Q30: The time estimate that represents the best
Q31: If an activity has a late start
Q32: Reducing a project's completion time by dedicating
Q34: The second step to crash a project
Q35: The shortest possible time to complete an
Q36: When estimating the probability of completing a
Q37: A project's completion time variance is calculated
Q38: The third step to crash a project