When crashing a project, the project manager should focus on?
A) Noncritical activities
B) Lowest crash cost noncritical activities
C) Critical activities
D) Lowest crash cost critical activities
Correct Answer:
Verified
Q86: An activity with a slack time greater
Q87: A critical path activity?
A) Has zero slack
Q88: A contractor indicates that he will be
Q89: A noncritical path activity?
A) Has zero slack
Q90: In a project, how many critical paths
Q92: When crashing a project, how many critical
Q93: An activity with a slack time of
Q94: A supplier indicates that he will not
Q95: A project's activities and the relationships between
Q96: A list of possible substitute workers has