Inventory held downstream of the bottleneck process is represents which of the following?
A) Drum
B) Buffer
C) Rope
D) Neither the drum, buffer, nor the rope
Correct Answer:
Verified
Q28: Having _ manufacturing flexibility is desirable.
A) Increased
B)
Q29: The scheduling of work releases to a
Q30: Material flow analysis can help to answer
Q31: Procedure and behavioral constraints include all of
Q32: Evaluating a process for effectiveness, quality, and
Q34: In an organization, something that keeps the
Q35: The Theory of Constraints was popularized by
Q36: Automation and standardized procedures are often used
Q37: Physical constraints include all of the following
Q38: Constraints can be overcome by all of