Assume that an assembly line has three tasks that must be completed (in order, A, B, and C) . The tasks have processing times of 9, 9, and 11 minutes per unit, respectively. If the assembly line operates for 400 minutes per day with a desired output of 70 units per day, what is the takt time?
A) 13.8 units per minute
B) 5.7 units per minute
C) 0.4 units per minute
D) Cannot be determined from the information given
Correct Answer:
Verified
Q71: Assume that an assembly line has three
Q72: Assume that an assembly line has three
Q73: If an assembly line has a target
Q74: Takt time is calculated by which of
Q75: If an assembly line operates for 420
Q77: Assembly line efficiency is calculated by which
Q78: Assume that an assembly line has three
Q79: Product-focused process layouts can lead to all
Q80: A good process-focused layout should seek to?
A)
Q81: A layout in which the manufactured unit
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents