Assume that an assembly line has three tasks that must be completed (in order, A, B, and C) . The tasks have processing times of 9, 9, and 11 minutes per unit, respectively. If the assembly operates for 400 minutes per day with a desired output of 70 units per day, what is the efficiency of the assembly line?
A) 84%
B) 64%
C) 94%
D) Cannot be determined from the information given
Correct Answer:
Verified
Q64: Assume that an assembly line has three
Q65: Assume that an assembly line has three
Q66: Assume that an assembly line has three
Q67: Wait time in a process-focused layout is
Q68: A focus of material flow in a
Q70: If an assembly line has an efficiency
Q71: Assume that an assembly line has three
Q72: Assume that an assembly line has three
Q73: If an assembly line has a target
Q74: Takt time is calculated by which of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents