Two jobs (J1 and J2) are scheduled on two workcenters (WCA and WCB) . J1 starts at time 0 on WCA and finishes on that workcenter at time 5. J2 starts at time 0 on WCB and finishes at time 3. J2 then starts on WCA at time 5 and finishes at time 9. What is the average queue time of these jobs?
A) 0
B) 1
C) 2
D) Cannot be determined from the information given
Correct Answer:
Verified
Q29: Two jobs (J1 and J2) are scheduled
Q30: What type of chart is often used
Q31: Which job shop dispatch rule tends to
Q32: Two jobs (J1 and J2) are to
Q33: Scheduling jobs into the future based upon
Q35: What type of rules determine which job
Q36: Two jobs (J1 and J2) are to
Q37: Which job shop dispatch rule schedules the
Q38: The average amount of time a job
Q39: The total elapsed time to complete a