In a work center, Machine A has a 10-minute set-up time per batch and a 2-minute per unit run time. Machine B performs the identical function but has a set-up time of 30 minutes and a 1-minute run time per unit. The work center makes products in batches ranging from 1 unit to 100 units. Assuming capacity is not a limitation on either Machine, in order to minimize the total processing time, on which batches should Machine B be used?
A) All batches should be run on Machine B.
B) Batches of more than 20 units should be run on Machine B.
C) Batches of fewer than 80 units should be run on Machine B.
D) Batches with up to 50 units should be run on Machine B.
E) No batches should be run on Machine B.
Correct Answer:
Verified
Q34: Assume a fixed cost for a process
Q35: A customer order decoupling point is where
Q36: Assume a fixed cost for a process
Q37: A project layout is only used for
Q38: Which of the following basic types of
Q40: You are hired as a consultant to
Q41: This tool defines how parts go together,
Q42: Here the firm works with the customer
Q43: Suppose that you have two processes A
Q44: A production environment where the customer is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents